Class & Class & Day & Topic & Reading & Problems & Labs & Lecturer \\
 \hline                              
1 & 08/26 & Tue & Overview & 1 & 0 &   & Both \\
2 & 08/28 & Thu & Bits and Bytes & 2.1 & 2.44, 2.45, & L1  Out & droh \\
3 & 09/02 & Tue & Integers & 2.2--2.3 & 2.49, 2.54 &   & droh \\
4 & 09/04 & Thu & Floating Point & 2.4--2.5 & 2.59, 2.60, 2.61 &   & droh \\
5 & 09/09 & Tue & Machine Prog I - Overview & 3.1--3.5 & 3.31 &   & TBD \\
6 & 09/11 & Thu & Machine Prog II - Control & 3.6 & 3.34 & L1 Due, L2 Out & droh \\
7 & 09/16 & Tue & Machine Prog III- Procs & 3.7 & 0 &   & droh \\
8 & 09/18 & Thu & Machine Prog IV- Data & 3.8--3.11 & 3.36 &   & droh \\
9 & 09/23 & Tue & Mach. Prog V - Advanced & 3.12--3.13, 3.16 & 3.24 &   & droh \\
10 & 09/25 & Thu & Program Optimization & 5.1--5.6 & 0 & L2 Due, L3 Out & droh \\
11 & 09/30 & Tue & Memory Hierarchy & 6.1--6.4 & 6.21, 6.23, 6.24 &   & agn \\
12 & 10/02 & Thu & Cache Memories & 6.5--6.8 & 6.25, 6.26, 6.27 & L3 Due & agn \\
13 & 10/07 & Tue & Exam 1 & Time and Location TBA & 0 &   & 0 \\
14 & 10/09 & Thu & Linking & 7 & 7.8, 7.12 & L4 Out & droh \\
15 & 10/14 & Tue & Except. Control Flow I & 8.1--8.4 & 8.10, 8.11 &   & agn \\
16 & 10/16 & Thu & Except. Control Flow II & 8.5--8.8 & 8.19 & L4 Due, L5 Out & agn \\
17 & 10/21 & Tue & Virtual Memory & 10.1--10.6 & 10.11, 10.12, 10.13 &   & agn \\
18 & 10/23 & Thu & P6/Linux Memory System & 10.7--10.8 & 10.14 & 0 & agn \\
19 & 10/28 & Tue & Dynamic Storage Alloc I & 10.9 & 10.15, 10.16 & L5 Due, L6 Out & agn \\
20 & 10/30 & Thu & Dynamic Storage Alloc II & 10.10--10.13 & 10.18 &   & agn \\
21 & 11/04 & Tue & System-level I/O & 11 & 11.7 & 0 & agn \\
22 & 11/06 & Thu & Network Programming & 12.1--12.3 & 0 & L6 Due, L7 Out & agn \\
23 & 11/11 & Tue & Web Services & 12.4 & 0 & 0 & droh \\
24 & 11/13 & Thu & Exam 2 & 12.5--12.7 & 12.10 & =schedule.xl!G27 & droh \\
26 & 11/20 & Thu & Web Services & 12.8 & 0 & 0 & 0 \\
27 & 11/25 & Tue & Concurrency & 13.1--13.3 & 13.22, 13.23 & 0 & agn \\
28 & 11/27 & Thu & Synchronization & 13.4-13.8 & 13.24 & 0 & agn \\
29 & 12/02 & Tue & Time Measurement & 9 & 9.10, 9.11 & 0 & droh \\
30 & 12/04 & Thu & Wrap Up & 0 & 0 & L7 Due & Both \\