----- Original Message -----
Sent: Friday, February 01, 2002 5:40
PM
Subject: Booths for AV-TS R6 Units
To
all with R6 booths:
There have been reports from Steve Knecht (Marin, CA) and Robert
Pickett (Sales Rep, NC) that the existing screws on the feet of the R6 unit
are too short to accommodate the thickness of the metal booth mounting
brackets. Diebold engineering (Canton, OH) is investigating this issue
and will determine an effective solution. In the meantime, the R6
units can be placed into the booths without securing them so as to allow
operation for early voting requirements. Please
exercise caution that the R6 unit is transported separately from the
booth until it can be secured with the proper fasteners.
Sincerely,
Ian S. Piper
Diebold Election Systems,
Inc.