He will not accept financial or other considerations, including free
engineering designs, from material or equipment suppliers for specifying
their product.
[See Codes
10(a).,
III.5.a.
]
- Code is relevant when:
- Engineer specifies a material or equipment suppliers product
- Code is violated when:
- Engineer accepts financial consideration for specifying the product
OR
Engineer accepts other considerations, including free engineering designs, for specifying the product
- Code is not violated when
- Engineer does not accept financial consideration for specifying the product
AND
Engineer does not accept other considerations, including free engineering designs, for specifying the product